MOI UNIVERSITY

Office of the Deputy Vice Chancellor

Academics, Research, Extension and Student Affairs

UNIVERSITY EXAMINATIONS

2024/2025 Academic Year
Third Year Second Semester Examination
For the Degree of Bachelor of Science in Project Planning and Management and Bachelor of Business Management
Course Code: BBM 351 / BPM 316
Course Title: OPERATIONS RESEARCH
Date: 7th July, 2025
Time: 9:00 A.M. - 12:00 P.M.

INSTRUCTION TO CANDIDATES

Answer Question One and Any Other Three Questions

QUESTION FOUR

(a) Consider a project consisting of nine jobs with the following precedence relations and time estimates:

Activity Predecessor Optimistic Time (a) Most Probable Time (m) Pessimistic Time (b)
A-258
BA6912
CA678
DB, C147
EA888
FD, E51417
GC31221
HF, G369
IH5811

(i) Construct the project network (4 marks)

We construct the project network using the **Activity-on-Node (AON)** format.

Start | v A / | \ B C E \ / | D | \ | \ | F \ \ \ H | I | Finish

Note: A starts the project; B and C follow A; D follows B and C; E follows A; F follows D and E; G follows C; H follows F and G; I follows H.

(ii) Find the expected duration and the variance of each activity (4 marks)

We use the **PERT formula**:

Activity a m b Expected Time Variance
A25851.00
B691291.00
C67870.11
D14741.00
E88880.00
F51417134.00
G31221129.00
H36961.00
I581181.00

(iii) What is the expected length of the project and its variance? (4 marks)

Step 1: Forward Pass (Calculate ES and EF)

ActivityESEF = ES + t
A05
B514
C512
D1418
E513
F1831
G1224
H3137
I3745

Step 2: Backward Pass (Calculate LS and LF)

ActivityLFLS = LF - t
I4537
H3731
F3118
G3119
D1814
E1810
C147
B145
A50

Step 3: Slack and Critical Path

Critical Path: A → B → D → F → H → I

Total Duration: 5 + 9 + 4 + 13 + 6 + 8 = 45 days

Variance: 1 + 1 + 1 + 4 + 1 + 1 = 9.00

(iv) What is the probability of completing the project in 50 days? (3 marks)

We use the **Z-score** to estimate the probability:

Z-score:

Z = (Target time - Mean) ÷ Standard deviation

Z = (50 - 45) ÷ 3 = 5 ÷ 3 = 1.67

From the standard normal distribution table:

Cumulative probability for Z = 1.67 is approximately 0.9525

✅ Answer: 95.25%

(b) Consider the following activities and their durations:

Activity Preceding Activity Duration
A-3
B-4
CA9
DA3
EA8
FC2
GC3
HC2
JB, D6
KF, J1
LE, H, G, K4

(i) Construct CPM network (3 marks)

We construct the CPM network using **Activity-on-Node (AON)** format:

Start | v A / | \ C D E |\ | | F G H L | | | J K | Finish

(ii) Determine the critical path (2 marks)

Critical Path: A → C → F → J → K → L

Total Duration: 3 + 9 + 2 + 6 + 1 + 4 = 25 days

(iii) Compute total floats and free floats for non-critical activities (4 marks)

Activity Duration ES EF LS LF Total Float Free Float
B40461066
D336111488
G31215131611
H21214192177
E831113211010